Headline: At 12:26 today, Christmas Day, electricity supply through the ESTLINK 2 connecting Finland an Estonia was interrupted.
Short Summary: Electricity via the ESTLINK 2 undersea cable between Finland and Estonia was interrupted. Investigation ongoing, with evidence of possible ship anchor involvement.
On December 25, 2024, at 12:26 UTC, electricity supply through ESTLINK 2, the undersea power cable connecting Finland and Estonia, was interrupted. The Finnish National Grid (Fingrid) reported the outage and launched an investigation, involving Estonian authorities and the Finnish Border Guard. MarineTraffic data indicates the Hong Kong-flagged vessel Xin Xin Tian 2 crossed the cable at the time of the interruption. The incident is under investigation.